Meat and Poultry Processing Standards
PRODUCTION & PROCESS CONTROLS Version 4.0
Click to view
Key – Those standards which have greater significance (all other standards are normal)
Recommendation – Those which do not affect certification
New – A completely new standard which the member must now adhere to
Revised – A standard that has changed and requires the member to take some different or additional action to before
Upgraded – The standard has been upgraded to a Key standard or from a Recommendation to a full standard
Appendix – Referenced in ‘How you will be measured’. Indicates that additional information is provided in the Appendices, which are available at the end of each section.
MP.PC.1
The flow of the process from intake to dispatch must be controlled in order to prevent cross contamination between production areas, by people, equipment or waste
How you will be measured
MP.PC.1.a
MP.PC.1.b
MP.PC.2
Systems must be in place to thaw frozen products in a controlled manner
How you will be measured
MP.PC.2.a
MP.PC.2.b
Thawing protocol
MP.PC.3
Equipment settings must only be completed by trained and authorised staff (New)
How you will be measured
MP.PC.3.a
MP.PC.4
Where online check weighers are used, a procedure must be documented to cover operation and testing (New)
How you will be measured
MP.PC.4.a
MP.PC.5
Packaging must be purchased from approved sources (Revised)
How you will be measured
MP.PC.5.a
MP.PC.5.b
MP.PC.5.c
Packaging approval
MP.PC.6
Packaging must be suitable for its intended use, as confirmed by up to date specifications (Revised)
How you will be measured
MP.PC.6.a
MP.PC.6.b
MP.PC.6.c
MP.PC.6.d
Packing specification
Specifications review
MP.PC.7
A documented procedure for the receipt of packaging must be in place detailing checks that must be carried out
How you will be measured
MP.PC.7.a
Documented procedures
MP.PC.8
Packaging must be stored in a suitable, clean, pest-free area
How you will be measured
MP.PC.8.a
MP.PC.8.b
MP.PC.9
Packaging must be able to be moved to the point of use, without the risk of contamination
MP.PC.10
Systems must be in place to prevent the use of obsolete packaging, including labels (New)
How you will be measured
MP.PC.10.a
Documented procedures
MP.PC.11
Systems must be in place to ensure that products are packed and labelled with the correct packaging/ labelling (Revised)
How you will be measured
MP.PC.11.a
MP.PC.11.b
MP.PC.11.c
MP.PC.11.d
MP.PC.11.e
Documented procedure, Red Tractor artwork approval
MP.PC.12
Cooking instructions on packaging must be validated (New)
How you will be measured
MP.PC.12.a
MP.PC.13
Systems must be in place to minimise the risk of contamination of product by metal (Revised)
How you will be measured
MP.PC.13.a
MP.PC.13.b
MP.PC.13.c
MP.PC.13.d
MP.PC.13.e
Metal risk assessment and procedures
MP.PC.14
Documented procedures must be implemented when the metal detector or X-ray equipment detects contaminated product (Revised)
How you will be measured
MP.PC.14.a
Metal detection procedure
MP.PC.15
Where a product is found to be contaminated with metal, the source of contamination must be investigated and action taken to prevent a reoccurrence
MP.PC.16
Metal detectors or X-ray equipment must be tested regularly for correct functioning, in accordance with a documented procedure (Revised)
How you will be measured
MP.PC.16.a
MP.PC.16.b
Metal detecting test procedures
MP.PC.17
Where a test on a metal detector or X-ray equipment fails, corrective actions must be implemented
How you will be measured
MP.PC.17.a
Corrective action
MP.PC.18
Where a site is handling known allergens, risk assessed procedures must be in place to minimise the risk of allergen contamination of products (Revised)
How you will be measured
MP.PC.18.a
MP.PC.18.b
Risk assessed procedures
MP.PC.19
A risk assessed schedule of finished product testing must be in place (Revised)
How you will be measured
MP.PC.19.a
MP.PC.19.b
MP.PC.19.c
MP.PC.19.d
Testing schedule and results
MP.PC.20
Where testing identifies non-conforming products, corrective action must be implemented (Revised)
How you will be measured
MP.PC.20.a
MP.PC.20.b
Corrective action
MP.PC.21
Any testing carried out that is critical to product safety and legality, is to internationally recognised methods in appropriately accredited laboratories
How you will be measured
MP.PC.21.a
Lab certificate
MP.PC.22
Non-conforming products must be dealt with appropriately, in accordance with the site’s documented procedure
How you will be measured
MP.PC.22.a
MP.PC.22.b
MP.PC.22.c
MP.PC.22.d
Non-conformity root cause
MP.PC.23
Systems must be in place to check the fitness of livestock for human consumption (Revised)
How you will be measured
MP.PC.23.a
MP.PC.23.b
MP.PC.23.c
MP.PC.23.d
MP.PC.24
Systems must be in place to ensure that livestock are of suitable cleanliness at slaughter
How you will be measured
MP.PC.24.a
MP.PC.24.b
MP.PC.24.c
Clean livestock policy
MP.PC.25
Where the monitoring identifies suppliers failing to meet the sites requirements, corrective action must be implemented (Revised)
How you will be measured
MP.PC.25.a
MP.PC.25.b
Corrective actions
MP.PC.26
Systems must be in place to prevent cross contamination between species on the slaughter line in multi species abattoirs
How you will be measured
MP.PC.26.a
MP.PC.27
Risk assessed systems that minimise contamination of the carcase must be implemented
How you will be measured
MP.PC.27.a
MP.PC.27.b
MP.PC.27.c
MP.PC.27.d
MP.PC.27.e
MP.PC.28
Systems must be in place to identify, isolate and deal with diseased, dirty or otherwise contaminated carcases
How you will be measured
MP.PC.28.a
MP.PC.28.b
MP.PC.28.c
MP.PC.28.d
MP.PC.29
Risk assessed systems that minimise contamination of the carcase must be implemented (Revised)
How you will be measured
MP.PC.29.a
MP.PC.29.b
MP.PC.29.c
MP.PC.29.d
MP.PC.29.e
MP.PC.30
Systems must be in place to identify, isolate and deal with diseased, dirty or otherwise contaminated carcases
How you will be measured
MP.PC.30.a
MP.PC.30.b
MP.PC.30.c
MP.PC.30.d
MP.PC.30.e
MP.PC.30.f
MP.PC.31
Systems must be in place to minimise the risk of staff handling raw poultry meat coming into contact with packagings
More Standards
Download the Meat and Poultry Processing Standards Manual (V4)
The Red Tractor Meat and Poultry Processors Scheme is part of the Red Tractor Food Assurance Scheme assuring food safety, animal welfare, hygiene environmental protection through every part of the food chain.
The Standards provide clear and credible assurance for all and should be read in conjunction with the Member Rules which all members are bound by.